Saturday, 22 December 2012

PMP exam formulas

. PERT
(P + 4M + O )/ 6 Pessimistic, Most Likely, Optimistic
2. Standard Deviation
(P - O) / 6
3. Variance
[(P - O)/6 ]squared
4. Float or Slack
LS-ES and LF-EF
5. Cost Variance
EV - AC
6. Schedule Variance
EV - PV
7. Cost Perf. Index
EV / AC
8. Sched. Perf. Index
EV / PV
9. Est. At Completion (EAC)
BAC / CPI,
AC + ETC -- Initial Estimates are flawed
AC + BAC - EV -- Future variance are Atypical
AC + (BAC - EV) / CPI -- Future Variance would be typical
10. Est. To Complete
Percentage complete
EAC - AC
EV/ BAC
11. Var. At Completion
BAC - EAC
12. To Complete Performance Index TCPI
Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete is less than planned. How efficient must the project team be to complete the remaining work with the remaining money?
( BAC - EV ) / ( BAC - AC )
13. Net Present Value
Bigger is better (NPV)
14. Present Value PV
FV / (1 + r)^n
15. Internal Rate of Return
Bigger is better (IRR)
16. Benefit Cost Ratio
Bigger is better ((BCR or Benefit / Cost) revenue or payback VS. cost)
Or PV or Revenue / PV of Cost
17. Payback Period
Less is better
Net Investment / Avg. Annual cash flow.
18. BCWS
PV
19. BCWP
EV
20. ACWP
AC
21. Order of Magnitude Estimate
-25% - +75% (-50 to +100% PMBOK)
22. Budget Estimate
-10% - +25%
23. Definitive Estimate
-5% - +10%
24. Comm. Channels
N(N -1)/2
25. Expected Monetary Value
Probability * Impact
26. Point of Total Assumption (PTA)
((Ceiling Price - Target Price)/buyer's Share Ratio) + Target Cost
Sigma σ
  • 1σ = 68.27%
  • 2σ = 95.45%
  • 3σ = 99.73%
  • 6σ = 99.99985%
Return on Sales ( ROS )
 
Net Income Before Taxes (NEBT) / Total Sales OR
Net Income After Taxes ( NEAT ) / Total Sales
Return on Assets( ROA )
 
NEBT / Total Assets OR
NEAT / Total Assets
Return on Investment ( ROI )
NEBT / Total Investment OR
NEAT / Total Investment
Working Capital
Current Assets - Current Liabilities
Discounted Cash Flow
Cash Flow X Discount Factor
Contract related formulas
Savings = Target Cost – Actual Cost

Bonus = Savings x Percentage

Contract Cost = Bonus + Fees

Total Cost = Actual Cost + Contract Cost







Critical Path formulas 
Forward Pass: (Add 1 day to Early Start)                EF = (ES + Duration - 1)
Backward Pass: (Minus 1 day to Late Finish)
LS = (LF - Duration + 1)
ES = Early Start; EF = Early Finish;
LS = Late Start; LF = Late Finish

EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) - (Investment Capital X % Cost of Capital) EVA - Economic Value Add Benefit Measurement - Bigger is better

Source Selection = (Weightage X Price) + (Weightage X Quality)




No comments:

Post a Comment