| 
. PERT | 
(P + 4M + O )/ 6 Pessimistic, Most Likely, Optimistic | 
| 
2. Standard Deviation | 
(P - O) / 6 | 
| 
3. Variance | 
[(P - O)/6 ]squared | 
| 
4. Float or Slack | 
LS-ES and LF-EF | 
| 
5. Cost Variance | 
EV - AC | 
| 
6. Schedule Variance | 
EV - PV | 
| 
7. Cost Perf. Index | 
EV / AC | 
| 
8. Sched. Perf. Index | 
EV / PV | 
| 
9. Est. At Completion (EAC) | 
BAC / CPI, 
AC + ETC -- Initial Estimates are flawed 
AC + BAC - EV -- Future variance are Atypical 
AC + (BAC - EV) / CPI -- Future Variance would be typical | 
| 
10. Est. To Complete 
Percentage complete | 
EAC - AC 
EV/ BAC | 
| 
11. Var. At Completion | 
BAC - EAC | 
| 
12. To Complete Performance Index TCPI | 
Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete is less than planned. How efficient must the project team be to complete the remaining work with the remaining money? 
( BAC - EV ) / ( BAC - AC ) | 
| 
13. Net Present Value | 
Bigger is better (NPV) | 
| 
14. Present Value PV | 
FV / (1 + r)^n | 
| 
15. Internal Rate of Return | 
Bigger is better (IRR) | 
| 
16. Benefit Cost Ratio | 
Bigger is better ((BCR or Benefit / Cost) revenue or payback VS. cost) 
Or PV or Revenue / PV of Cost | 
| 
17. Payback Period | 
Less is better 
Net Investment / Avg. Annual cash flow. | 
| 
18. BCWS | 
PV | 
| 
19. BCWP | 
EV | 
| 
20. ACWP | 
AC | 
| 
21. Order of Magnitude Estimate | 
-25% - +75% (-50 to +100% PMBOK) | 
| 
22. Budget Estimate | 
-10% - +25% | 
| 
23. Definitive Estimate | 
-5% - +10% | 
| 
24. Comm. Channels | 
N(N -1)/2 | 
| 
25. Expected Monetary Value | 
Probability * Impact | 
| 
26. Point of Total Assumption (PTA) | 
((Ceiling Price - Target Price)/buyer's Share Ratio) + Target Cost | 
| 
Sigma σ | 
 | 
| 
Return on Sales ( ROS )  | 
Net Income Before Taxes (NEBT) / Total Sales OR 
Net Income After Taxes ( NEAT ) / Total Sales | 
| 
Return on Assets( ROA )  | 
NEBT / Total Assets OR 
NEAT / Total Assets | 
| 
Return on Investment ( ROI ) | 
NEBT / Total Investment OR 
NEAT / Total Investment | 
| 
Working Capital | 
Current Assets - Current Liabilities | 
| 
Discounted Cash Flow | 
Cash Flow X Discount Factor | 
| 
Contract related formulas | 
Savings = Target Cost – Actual Cost Bonus = Savings x Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost | 
Critical Path formulas 
Forward Pass: (Add 1 day to Early Start)                EF = (ES + Duration - 1)
Backward Pass: (Minus 1 day to Late Finish)
LS = (LF - Duration + 1)
ES = Early Start; EF = Early Finish;
LS = Late Start; LF = Late Finish
Backward Pass: (Minus 1 day to Late Finish)
LS = (LF - Duration + 1)
ES = Early Start; EF = Early Finish;
LS = Late Start; LF = Late Finish
EVA = Net Operating Profit After Tax - Cost of Capital (Revenue - Op. Exp - Taxes) - (Investment Capital X % Cost of Capital) EVA - Economic Value Add Benefit Measurement - Bigger is better
Source Selection = (Weightage X Price) + (Weightage X Quality)
 
 
No comments:
Post a Comment